The Brick Yard – North

Brick Yard

Project Description

Client/Builder/Developer:   Jackson Shaw Company
Location:  13150 Mid Atlantic Blvd Laurel, Maryland
Market: Industrial
Size:  14.69 Acres
Zoning: RNC – Optional Method with MPDU Density Bonus
Density:  I-3, Industrial but Subject to I-1 Regulations

The Challenges

The Brick Yard was the last of an infill warehouse development on Mid Atlantic Blvd in Laurel, Maryland, 10 miles northeast of Washington, DC.  The development is comprised of 125 master-planned acres that includes over 1,200 residential units and office, warehouse, Corporate and Regional Headquarters buildings.  All buildings were built to Green Building Development Standards and met LEED Silver Certification requirements.  The property was originally home to the Washington Brick Company and utilized for mining and brick manufacturing.  During the time of mining fossil deposits were discovered on the property.  Our clients recognized their historic value donated land and resources to complete a 7.5 acre park dedicated to dinosaur discovery.  The 70 acre industrial section is planned for over 700,000 square feet of multi-purpose industrial buildings.

GLW was brought on as part of a design-build team responsible for the site design, civil engineering (site grading, storm drain and utility design), tree conservation and landscaping of a 236,000 square foot warehouse building (the largest warehouse in the development) and its associated appurtenances.

The building and site needed to be designed to allow for a possible office expansion and a second access from Cedarhurst Drive.

The Solution

GLW site designers not only sited the largest warehouse within the development they also provided future expansion space via detailed grading and phasing of construction.  After Site, Landscape and Tree Conservation plans were approved by government agencies; GLW coordinated all site engineering issues with team members and completed the project within the forecasted schedule.  During permit review a new tenant was signed requiring changes to the building entrance location and pedestrian and vehicular access.  Detailed site plan revisions were made and coordinated with the architect to minimize any delay in the permit process.

 

Steeplechase

02 multi tenant

Project Description

Client/Builder/Developer:  Atapco Ritchie Interchange, Inc.
LocationRitchie Marlboro Road, Prince George’s County, Maryland
MarketIndustrial
Size110.26 Acres
Zoning: I-1, Light Industrial, Retail
Density:  N/A

Recent Projects

The Challenge

Steeplechase is a 110-acre mixed-use (flex-office/warehouse and retail) development located on the Capital Beltway at the Ritchie Marlboro interchange. Prince George’s County awarded Steeplechase a Foreign Trade Zone status because of its excellent visibility along I-495 and because it offers 28 individual retail spaces of 50,000 to 500,000 square feet. Initial plan approvals permitted a retail component in the Industrial Zone provided that 10 retail parcels would be subject to Site Plan approval by the Planning Board. This would ensure design compatibility in architecture, building materials, signage, entry walls and landscaping between the various retail uses. The remaining industrial/warehouse parcels have owners/tenants with their own needs and specifications. The parcels are located around a stream and associated wooded areas, floodplains, steep slopes and wetlands.

The Solution

GLW was responsible for site planning, landscape architecture, civil engineering (site layout, site grading, storm drain/SWM design) and construction permitting for each of the parcels. Design requirements ranged from siting massive power requirements for a medical cannabis grower to stormwater storage in large underground pipes to allow siting our client’s building. On another parcel, GLW recommended a wetland consultant review an outdated wetland delineation. The updated wetland allowed for an improved site design that protected wetlands and increased the development envelope for our client. Throughout the development, parking areas and buildings were located to avoid sensitive environmental features and minimize the amount of earth moving required.